02 / Dublin

2026Current

Dawson Street

Heritage Mixed-Use Refurbishment

Dawson Street - site hoarding on the Dublin street frontage beside the Luas line

Overview

Location
Dublin, Ireland
Role
Principal Contractor
Status
Current
On Site Since
April 2026

Dating from approximately 1740, this five-storey historic building in Dublin city centre is undergoing conservation-led refurbishment under DGW's principal contractor appointment.

The completed development will provide commercial accommodation and grey-box at basement and ground level, with luxury residential apartments across levels one to three.

Works involve controlled soft strip, complete construction and refurbishment, luxury residential finishes, commercial grey-box works and roof works - all coordinated within restricted city-centre access, with Luas infrastructure immediately adjacent.

Photography

01 images

Scope & Delivery

01

Conservation-Led Refurbishment

02

Controlled Soft Strip

03

Complete Construction & Refurbishment

04

Luxury Residential Finishes

05

Commercial Grey-Box Works

06

Roof Works

07

Architecture Coordination

08

M&E Coordination

09

Conservation Stakeholder Liaison

Challenges

  • 01

    Restricted city-centre access

  • 02

    Permits and delivery logistics

  • 03

    Luas infrastructure immediately adjacent

  • 04

    Conservation stakeholder requirements